Topics · build-out

The AI data center pipeline

Method

141 announced projects of at least 100 MW or USD 1 bn, in 29 countries: up to 90.9 GW at full build-out.

Announced ≠ built. Capacity and investment are developers' own claims, often multi-phase and “up to”; they are shown as stated, never as measured, and some projects pause or lose partners. Status reflects the latest source we could verify.

141 projects · up to 90.9 GW announced

Announced capacity by status

under construction36,914 MW
permitting27,600 MW
announced16,455 MW
partially operational9,360 MW
operational300 MW
paused274 MW
loading map…
Skip the list of projects
under constructionai training2025 → 2027

Fermi America Project Matador (HyperGrid campus)

Carson County, near Amarillo, Texas, United States · Fermi America with Texas Tech University System, TensorWave (tenant)

Announced capacity
11,000 MW
Power (stated)
On-site gas (6 GW permitted), planned AP1000 nuclear, solar, batteries, grid

Up to 11 GW power at full buildout (DCD 2025); Fermi now cites 17 GW planned, ~6 GW permitted (Aug 2026). First tenant TensorWave 222 MW, expandable >650 MW

DCD confirms 11 GW, 5,769 acres, Texas Tech partnership; Fermi release (Aug 2026) confirms construction underway, 17 GW planned/6 GW permitted, >$1.5bn invested to date (not total capex), TensorWave 222 MW from H2 2027.

  • DCD, Fermi America acquires 600MW of gas turbines for 11GW AI mega campus in Amarillo, Texas (2025-07-03)
  • Fermi America, Fermi Announces Binding Lease Agreement with TensorWave (2026-08-10)
permittingai training

Wonder Valley AI Data Centre Park

Greenview Industrial Gateway, near Grande Prairie, Alberta, Canada · O'Leary Digital / O'Leary Ventures with Municipal District of Greenview

Announced capacity
7,500 MW
Investment (stated)
C$70bn proposed (CBC) - not converted

7.5 GW proposed (stated by Kevin O'Leary, CBC)

CBC (Apr 2026) confirms $70bn / 7.5 GW proposal, ~40 km south of Grande Prairie, EIA exemption but permits still required.

  • CBC News, Wonder Valley AI Data Centre exempt from provincial environmental impact assessment, still needs permits (2026-04-10)
under constructionai training2024-12 → 2030

Meta Hyperion (Richland Parish Data Center)

Richland Parish, Louisiana, United States · Meta with Meta, Blue Owl Capital (JV), Entergy Louisiana

Announced capacity
5,000 MW
Announced investment
USD 50 bn
Power (stated)
Seven new natural gas plants, three grid-scale batteries, nuclear uprates and PPAs (Meta)

5 GW compute capacity stated by Meta; 2 GW by 2030 per Meta spokesperson (TechCrunch)

Meta post (Jul 2026): 5 GW, >$50bn in region, broke ground Dec 2024; TechCrunch: 2 GW online by 2030.

Local events at this site: Louisiana regulators approve Entergy gas plants for Meta campus (2025-08-20)

  • Meta, Deepening our investment in Richland Parish, Louisiana (2026-07-13)
  • TechCrunch, Mark Zuckerberg says Meta is building a 5GW AI data center (2025-07-14)
permittingmixed2024-09

Scala AI City

Eldorado do Sul, Rio Grande do Sul, Brazil, Brazil · Scala Data Centers (DigitalBridge)

Announced capacity
4,750 MW
Announced investment
USD 50 bn, sources differ, see note

Up to 4.75GW at full build-out pitched by Scala; initial 54MW phase

R$300bn (US$50bn) full campus; initial R$3bn (US$490-500m)

DCD confirms 4.75GW, $50bn, 54MW first phase, zoning law Dec 2024; no 2025-2026 construction status fetched

  • DCD, Scala AI City: Scala pitches $50bn Brazil data center campus of up to 4.7GW (2024-09-11)
  • DCD, Brazilian local government passes law to support Scala's AI City data center campus (2024-12-20)
permittingmixed2025-05 → 2028

Tract Caldwell Valley Technology Park

Uhland, Caldwell County, Texas, United States · Tract with Bluebonnet Electric Cooperative, LCRA

Announced capacity
4,000 MW
Power (stated)
Bluebonnet/LCRA substation up to 1.6 GW; planned on-site gas generation

Up to 4 GW reported at full build-out (DCD); 1.6 GW on-site substation planned; first 250 MW contracted for Q1 2028

DCD confirms ~3,000 acres, up to 4 GW, 1.6 GW substation, first 250 MW Q1 2028. Status 'permitting' is an estimate (master-planned park, no construction confirmed).

  • DCD, Tract expands Austin data center park to 3,000 acres (2026-01-14)
partially operationalai training2024 → 2025

AWS Project Rainier (New Carlisle)

New Carlisle, St. Joseph County, Indiana, United States · Amazon (AWS) with Amazon Web Services, Anthropic (customer)

Announced capacity
2,200 MW
Announced investment
USD 11 bn

'more than 2.2 gigawatts' at full 30-building build-out (CNBC)

CNBC: $11bn, 1,200 acres, 7 buildings online Oct 2025, 30 buildings and >2.2 GW at full build.

  • CNBC, Amazon opens $11 billion AI data center Project Rainier in Indiana (2025-10-29)
announcedai training2025-10-15

Project Horizon (Poolside)

Longfellow Ranch, West Texas, United States · Poolside with CoreWeave (anchor tenant, exited Apr 2026)

Announced capacity
2,000 MW
Power (stated)
Permian Basin natural gas

2 GW on 568 acres, eight 250 MW phases (stated by Poolside); CoreWeave anchor deal for first 250 MW ended April 2026

Site stated only as Longfellow Ranch, West Texas; county not confirmed in fetched sources; coordinates withheld. DCD confirms 2 GW, 568 acres Longfellow Ranch, 250 MW first phase; MLQ (Apr 2026) confirms CoreWeave exit and Poolside seeking new anchor tenant. County not stated in fetched text - geocode approximately.

  • DCD, AI startup Poolside teams up with CoreWeave on 2GW data center in Texas (2025-10-16)
  • MLQ News, CoreWeave Ends 2 GW Texas Data Center Deal With Poolside (2026-04-04)
under constructionai training2025 → 2027

IREN Sweetwater Hub

Sweetwater, Texas, United States · IREN

Announced capacity
2,000 MW
Power (stated)
ERCOT grid; 1,400 MW bulk substation at Sweetwater 1

2 GW stated by IREN: Sweetwater 1 1,400 MW + Sweetwater 2 600 MW; 2,200 acres

IREN release (Sep 2026) confirms 1,400+600 MW, Sweetwater 1 substation energized 2026, 300 MW gross data center capacity under construction for Q4 2027. announced_date approximate.

  • IREN via GlobeNewswire, IREN's 2GW Sweetwater Hub Included as Base Load in ERCOT Batch Zero (2026-09-08)
  • IREN, Sweetwater Data Center | 2,000MW AI Campus in Texas (2026)
under constructionunknown2026-09

Aligned Project Phoenix

Shippingport Industrial Park, Shippingport, Beaver County, Pennsylvania, United States · Aligned Data Centers with Frontier Group of Companies (site owner)

Announced capacity
2,000 MW
Power (stated)
Dedicated on-site natural gas power (redeveloped Shippingport/Bruce Mansfield site)

2 GW stated by Aligned; three facilities

DCD confirms 2 GW, groundbreaking, Beaver County, on-site power. $10bn figure seen only as 'economic impact' in search snippets - not used as capex.

  • DCD, Aligned breaks ground on gigawatt-scale data center campus in Pennsylvania (2026-09-17)
under constructionai training2025 → 2028

Project Jade (Cheyenne AI campus)

Laramie County, south of Cheyenne, Wyoming, United States · Tallgrass / undisclosed data center customer with Tallgrass, Black Hills Corp., Crusoe (exited 2026)

Announced capacity
1,800 MW
Investment (stated)
Tallgrass energy infrastructure $7bn;
Power (stated)
Tallgrass Cheyenne Power Hub / BFC Power: ~2.7 GW on-site natural gas generation

1.8 GW campus approved by Laramie County; designed to scale to 10 GW; on-site gas generation 2.7 GW (DCD)

Tallgrass energy infrastructure $7bn; total project cost 'could reach $50bn' (DCD) - not a firm capex figure

DCD confirms 1.8 GW, 10 GW potential, 2.7 GW gas, $7bn/$50bn; Cap City News (Jun 2026) confirms Crusoe exit, project continuing, site clearing/initial construction began 2026, Black Hills expects service early 2028.

  • DCD, Crusoe gets go-ahead for 1.8GW data center campus and power plant in Cheyenne, Wyoming (2026-01-08)
  • Cap City News, Project Jade data center to continue development without partner Crusoe (2026-06-12)

Candidate projects were drawn from operator, government and trade-press (DCD, Reuters, CNBC, company newsrooms) announcements of data-center campuses of >=100 MW announced capacity or >=USD 1 bn announced capex. Each MW, capex, date and status value was confirmed in the text of a source fetched between 2026-09-22 and 2026-09-24; values not found in fetched text are null. MW and capex are as announced/stated by the operator or reported by the cited source, not measured; announced MW is the largest stated build-out for the site. Capex is only filled when a USD figure is stated; other currencies and non-capex figures (economic impact, lease revenue, land purchase) are in capex_note. Status reflects the most recent dated source listed. Coordinates: Nominatim (OpenStreetMap) municipality or county centroid unless site coordinates are available from a linked atlas facility (location precision='site'). facility links link to the atlas data only when the same operator's facility with a matching name lies at the site. Missing a project? Send it with a source. Licence CC BY 4.0. Cite: Datacenter Atlas (2026). AI data center pipeline.